MAINS WATER SUPPLY

Apr 30, 2023

The absence of a mains water supply on the ground had been a long-standing issue of concern, as water had to be carried to the ground for the serving of refreshments.  The serving of refreshments was a tradition, and in fact laid down as a requirement.

Enquiries in 1953 about possible provision of a mains water supply to the ground, the need to carry water to the ground understandably having been reported as problematical, unfortunately resulted in the Committee reaching the view that the cost of £200 was beyond the reach of the Club’s finances.

In August 1960, two years before the ground was purchased by the Club, the first steps were taken to arrange for a mains water supply.  An on-site meeting took place with a representative of the Fylde Water Board to discuss laying a water pipe across the field, along the east side of the playing area. The architects concerned gave an assurance that any damage would be made good, and that the installation was expected to be completed prior to the commencement of 1961 Season.  Following a further visit of a Fylde Water Board representative in December, work commenced in January 1961, with connection to be made to the new water pipe, at the south-east corner of the ground, in readiness for the supply of water to the pavilion.

Unfortunately, it was found that the installation work had damaged the existing concrete practice wicket, beyond possible repair.  The Club therefore asked the Fylde Water Board if it would undertake to replace this in a different position, or alternatively compensate the Club for its loss, suggesting a figure of £50, in addition to the cost of re-seeding of the portion of the playing area which had been disturbed.  The Club also pressed for tidying up the clay and top-soil.  In response, the Fylde Water Board offered £25 compensation, but the Club expressed its dissatisfaction with the Water Board’s reaction, urging that the contractors install a replacement concrete wicket.  It was probably no great surprise that the Water Board did not reply to numerous attempts to achieve progress.

In November 1961 however, the reference in the Minutes Book to the Secretary being requested to write to the Fylde Water Board, asking for the concrete wicket to be two inches below the level of the ground, suggests that the Club’s determination to hold the Fylde Water Board’s contractors to the initial assurances that any damage would be made good, eventually prevailed !

By mid 1962, although the water pipe had been installed more than a year earlier, the necessary supply point to the pavilion had not been installed.  There being no subsequent mention in the Minutes Book of water supply issues, it is assumed that the Club’s demands were eventually satisfied.  

A totally separate ‘water’ issue, is the fact that running between the cricket playing surface and the Hazels residential development, is an underground pipe, believed to be approximately 30 inches diameter, which carries ‘raw’ (untreated) water from Haweswater in the Lake District, feeding reservoirs in Lancashire and Greater Manchester.  The 90 mile pipeline was commissioned in 1955, having taken 20 years to complete.

 

 


Latest articles